NEPSEtrading

Make smarter moves backed by machine learning. Join thousands of traders leveraging AI to maximize profits.

nepsetrading.com is an online news portal that provides insights into trading and investment by analyzing the stock market and the global economy. We create charts based on the analysis of various indicators. Please do not rely solely on this information for investment decisions. Self-study is crucial. Use this information only as an educational and informational resource.

Marketminds Investment Group Private Limited

DOIB Registration certificate no.: 4680-2081/2082

Director & Editor-in-chief: Dipesh Ghimire · 9802363868, 9851119988

Koteshwor 32, Kathmandu
01-5253221 · +977 9709066745

Contact support

Subscribe to our newsletter

Weekly insights from the NEPSE market in your inbox.

Market

  • Stocks
  • Sectors

Company

  • About Us
  • Our Team
  • Terms of Use
  • Our Policy
  • Training
  • Contact Us

Help

  • Support
  • Report
  • FAQ

© 2026 nepsetrading.com. All rights reserved.
Owned and operated by Marketminds Investment Group Private Limited.

Charts powered by TradingView

  • Home
  • Latest
  • Trending
  • Stock
  • Education
  • International
    1. News
    2. Investor
    3. Floods and Landslides Cause NPR 2.45 Billion in Damage to Nepal's Hydropower Sector, 1,100...
    बाढीपहिरोले जलविद्युत क्षेत्रमा २ अर्ब ४५ करोड रुपैयाँको क्षति, ११ सय मेगावाट उत्पादन बन्द
    Investor
    2 min read
    Published on September 29, 2024
    Dipesh Ghimire

    बाढीपहिरोले जलविद्युत क्षेत्रमा २ अर्ब ४५ करोड रुपैयाँको क्षति, ११ सय मेगावाट उत्पादन बन्दFloods and Landslides Cause NPR 2.45 Billion in Damage to Nepal's Hydropower Sector, 1,100 MW Power Production Halted

    नेपालको ऊर्जा, जलस्रोत तथा सिँचाइ मन्त्रालयले हालैको बाढी र पहिरोले जलविद्युत क्षेत्रमा करिब २ अर्ब ४५ करोड रुपैयाँ बराबरको क्षति पुर्याएको जनाएको छ। यो विपत्तिका कारण देशभर ११ सय मेगावाट विद्युत् उत्पादन ठप्प भएको छ भने सिँचाइ क्षेत्रमा पनि १ अर्ब ३५ करोड रुपैयाँ बराबरको क्षति पुगेको छ। यसले गर्दा देशको ऊर्जा आपूर्तिमा गम्भीर असर परेको छ।

    प्रमुख जलविद्युत् आयोजनामा क्षति

    १. माथिल्लो तामाकोसी जलविद्युत् आयोजना (४५६ मेगावाट):

    दोलखामा रहेको ४५६ मेगावाट क्षमताको माथिल्लो तामाकोसी जलविद्युत् आयोजना बन्द भएको छ। बाढीले आयोजनाको बाँध, नियन्त्रण कक्ष, र नहरहरूमा गम्भीर क्षति पुर्याएको छ। तीन दिनदेखि बन्द रहेको यस आयोजनालाई लामो समयसम्म पुनः सञ्चालन गर्न नसक्दा लोड व्यवस्थापनमा गम्भीर समस्या निम्तिन सक्ने खतरा रहेको छ। यो आयोजनाले देशको कुल ऊर्जा उत्पादनमा महत्वपूर्ण योगदान पुर्याउँदै आएको थियो।

    २. माण्डु खोला जलविद्युत् आयोजना (२२ मेगावाट):

    बागमती प्रदेशमा अवस्थित माण्डु खोला जलविद्युत् आयोजनाको पावरहाउस पूर्ण रूपमा डुबानमा परेको छ। कुलेखानी ड्याम खोल्दा आएको बाढीले पावरहाउसमा गम्भीर क्षति पुर्याएको छ, जसले आयोजनाको उत्पादन ठप्प बनाएको छ।

    ३. तल्लो हेवा खोला जलविद्युत् आयोजना (२२.१ मेगावाट):

    ताप्लेजुङमा रहेको तल्लो हेवा खोलाको २२.१ मेगावाटको आयोजना पनि बाढीले प्रभावित भएको छ। यस आयोजनाको पावरहाउस र अन्य संरचनाहरूमा क्षति पुगेको छ। गत वर्ष पनि बाढीले आयोजनाको पुल बगाएको थियो, जुन यस वर्ष फेरि बाढीले बगाएको छ।

    ४. माथिल्लो त्रिशुली २ जलविद्युत् आयोजना (२१६ मेगावाट):

    रसुवामा निर्माणाधीन २१६ मेगावाट क्षमताको माथिल्लो त्रिशुली २ आयोजनामा पनि बाढीपहिरोले गम्भीर क्षति पुर्याएको छ। आयोजनाको भौतिक संरचना र उपकरणहरूमा ठूलो क्षति भएको छ। यहाँ कार्यरत २१५ जना कर्मचारीलाई सुरक्षित स्थानमा सारिएको छ।

    प्रसारण लाइनहरूमा क्षति

    ५. खिम्ती लामोसाँघु प्रसारण लाइन:

    तामाकोसी नदीले खिम्ती लामोसाँघु प्रसारण टावर बगाएको छ, जसले २०० मेगावाट विद्युत् काठमाडौं ल्याउन अवरोध पुर्याएको छ। यो टावर बग्दा काठमाडौंमा विद्युत् आपूर्ति अवरुद्ध भएको छ। यसका साथै, तामाकोसीले थप ८०० मेगावाट प्रसारण गर्ने अर्को टावर पनि जोखिममा रहेको ऊर्जा मन्त्रालयले जनाएको छ।

    ६. काबेली करिडोर:

    काबेली करिडोरमा रहेका दुई प्रसारण टावर बाढीले क्षतिग्रस्त बनाएका छन्, जसका कारण इलाम र पाँचथरको फिदिममा विद्युत् सेवा अवरुद्ध भएको छ। यस क्षेत्रको विद्युत् सेवा पुनः सुचारु गर्ने प्रयास भइरहेको छ।

    ७. अन्य प्रसारण लाइनहरू:

    बाढीले सोलु करिडोर, कोशी करिडोर र दमक-गोदक प्रसारण लाइनमा पनि क्षति पुर्याएको छ। विशेषगरी दमकदेखि गोदकसम्मको प्रसारण लाइनको ५१ नम्बर टावर बाढीले बगाएको छ।

    निर्माणाधीन आयोजना

    १ हजार १० मेगावाट क्षमताका १५ निर्माणाधीन जलविद्युत् आयोजनामा पनि बाढीपहिरोले गम्भीर क्षति पुर्याएको छ। यी आयोजनाहरूको निर्माणमा ठूलो लगानी भएको छ, र यसको पुनर्निर्माणले लामो समय लाग्ने अनुमान गरिएको छ।

    ऊर्जा आपूर्तिमा गम्भीर समस्या

    बाढीपहिरोका कारण ११ सय मेगावाट विद्युत् उत्पादन रोकिएपछि नेपाल विद्युत् प्राधिकरणले भारतबाट ३ सय मेगावाट थप विद्युत् आयात गरेको छ। कुलमान घिसिङका अनुसार, यदि माथिल्लो तामाकोसी आयोजना लामो समयसम्म बन्द रह्यो भने देशभर लोडशेडिङको सम्भावना रहन्छ। साथै, सिँचाइ क्षेत्रतर्फ पनि ठूलो क्षति भएको छ, जसले कृषि उत्पादनमा असर पर्न सक्नेछ।

    पुनर्निर्माण र पुनर्स्थापना चुनौती

    बाढीपहिरोले पुर्याएको क्षतिको पूर्ण विवरण संकलन भइरहेको छ, र पुनर्निर्माणमा ठूलो समय र लगानी आवश्यक पर्ने देखिएको छ। विशेषगरी, जलविद्युत् आयोजना, प्रसारण लाइन र सिँचाइ संरचनाहरूको पुनर्स्थापना र सुधारमा ठूला चुनौतीहरू रहनेछन्।

    यस विपत्तिले नेपालको जलविद्युत् उत्पादनमा गहिरो असर पुर्याएको छ, र देशको ऊर्जा आपूर्ति व्यवस्थामा तत्कालीन र दीर्घकालीन समस्या सिर्जना भएको छ।

    Nepal’s Ministry of Energy, Water Resources, and Irrigation has reported that recent floods and landslides have caused approximately NPR 2.45 billion in damages to the country’s hydropower sector. This disaster has resulted in the shutdown of 1,100 MW of electricity production across the country, while the irrigation sector has also sustained damages amounting to NPR 1.35 billion. This has led to serious disruptions in the nation’s energy supply.

    Major Hydropower Projects Affected

    1. Upper Tamakoshi Hydropower Project (456 MW):
      Located in Dolakha, this 456 MW project has been shut down due to severe damage to its dam, control rooms, and canals. The project has been non-operational for three days, and the inability to resume operations in the near future poses a serious risk to load management. This project had been a major contributor to the country’s energy production.

    2. Mandu Khola Hydropower Project (22 MW):
      Situated in Bagmati Province, the Mandu Khola Hydropower project’s powerhouse has been completely submerged. The flood caused by the release of the Kulekhani Dam severely damaged the powerhouse, halting its production.

    3. Lower Hewa Khola Hydropower Project (22.1 MW):
      In Taplejung, the Lower Hewa Khola project has also been affected by flooding, damaging its powerhouse and other structures. Last year, a flood washed away the project’s bridge, and this year, the flood caused the same destruction.

    4. Upper Trishuli 2 Hydropower Project (216 MW):
      The 216 MW Upper Trishuli 2 project, under construction in Rasuwa, has also suffered severe damage from floods and landslides. The project’s physical infrastructure and equipment have been heavily affected, and 215 workers have been relocated to safety.

    Transmission Line Damages

    1. Khimti-Lamosanghu Transmission Line:
      The Tamakoshi River has swept away a tower of the Khimti-Lamosanghu transmission line, disrupting the flow of 200 MW of electricity to Kathmandu. Another tower, responsible for transmitting an additional 800 MW, is also at risk, according to the ministry.

    2. Kabeli Corridor:
      Two transmission towers in the Kabeli Corridor have been damaged by the floods, leading to a power outage in Ilam and Fidim in Panchthar. Efforts are underway to restore electricity in the area.

    3. Other Transmission Lines:
      The Solu Corridor, Koshi Corridor, and Damak-Godak transmission lines have also been affected. In particular, Tower 51 of the Damak-Godak line was swept away by the flood.

    Ongoing Construction Projects Fifteen hydropower projects, with a total capacity of 1,010 MW, currently under construction, have also suffered significant damage due to floods and landslides. Reconstruction of these projects will require substantial time and investment.

    Severe Energy Supply Challenges With the cessation of 1,100 MW of power production, the Nepal Electricity Authority has imported an additional 300 MW from India. According to Kulman Ghising, if the Upper Tamakoshi project remains offline for an extended period, there is a potential for load-shedding across the country. The agricultural sector is also expected to suffer due to damage in irrigation systems.

    Reconstruction and Restoration Challenges The full extent of the damage is still being assessed, and significant time and resources will be needed for reconstruction. The restoration of hydropower projects, transmission lines, and irrigation structures will pose major challenges in the coming days.

    This disaster has profoundly impacted Nepal’s hydropower production, creating immediate and long-term challenges for the nation’s energy supply system.

    Trending News

    • Trending14 Jun, 2026

      असारमा वाणिज्य बैंकको मुद्दति ब्याजदर थप घट्यो, ७ बैंकले दर घटाए

      Read news
    • Trending14 Jun, 2026

      नेपालकै सबैभन्दा ठूलो सम्पत्ति शुद्धीकरण मुद्दा अदालत पुग्यो, एक खर्ब ६ अर्बभन्दा बढी बिगो दाबी

      Read news
    • Trending14 Jun, 2026

      अमेरिका–इरान शान्ति सम्झौता निर्णायक मोडमा, पाकिस्तानले भन्यो — '२४ घण्टामा हस्ताक्षर सम्भव'

      Read news

    Related News

  • असारमा वाणिज्य बैंकको मुद्दति ब्याजदर थप घट्यो, ७ बैंकले दर घटाए
    Investor

    1 min read

    असारमा वाणिज्य बैंकको मुद्दति ब्याजदर थप घट्यो, ७ बैंकले दर घटाए

    NEPSE TRADING

    ·

    14 Jun, 2026

  • नेपालकै सबैभन्दा ठूलो सम्पत्ति शुद्धीकरण मुद्दा अदालत पुग्यो, एक खर्ब ६ अर्बभन्दा बढी बिगो दाबी
    Investor

    4 min read

    नेपालकै सबैभन्दा ठूलो सम्पत्ति शुद्धीकरण मुद्दा अदालत पुग्यो, एक खर्ब ६ अर्बभन्दा बढी बिगो दाबी

    NEPSE TRADING

    ·

    14 Jun, 2026

  • अमेरिका–इरान शान्ति सम्झौता निर्णायक मोडमा, पाकिस्तानले भन्यो — '२४ घण्टामा हस्ताक्षर सम्भव'
    Top

    1 min read

    अमेरिका–इरान शान्ति सम्झौता निर्णायक मोडमा, पाकिस्तानले भन्यो — '२४ घण्टामा हस्ताक्षर सम्भव'

    NEPSE TRADING

    ·

    14 Jun, 2026

  • शेयर बजारमा जलविद्युत कम्पनी : अनुत्तरित प्रश्नहरूको भारले थिचिएको लगानीकर्ता
    Investor

    5 min read

    शेयर बजारमा जलविद्युत कम्पनी : अनुत्तरित प्रश्नहरूको भारले थिचिएको लगानीकर्ता

    NEPSE TRADING

    ·

    12 Jun, 2026

  • नेपालको पुँजी बजार : तीन दशकको यात्रा, अझै अधुरो सुधार
    Investor

    3 min read

    नेपालको पुँजी बजार : तीन दशकको यात्रा, अझै अधुरो सुधार

    Dipesh Ghimire

    ·

    12 Jun, 2026